Project background

In a paper mill the allowed chloride concentration in the process water was regularly exceeded. Due to the persistently high chloride load, there was a risk of corrosion damage to the paper machine.

  PP 1 Prozesswasseraufbereitung Beitrag

Goal and challange

The plant was designed to achieve a permanent reduction of the chloride load to below 50 mg/l. This was possible despite strongly fluctuating inlet qualities of the sand filtered river water and a high biofouling potential.

Concept and realisation

Reverse osmosis was provided for the filtration of the river water pre-filtered on site by a gravel filter. To ensure a stable operation and a long lifetime of the membrane, special low-fouling membranes were selected. In addition, the plant was equipped with a special OSMO cleaning system (CIP), which enables the separate cleaning of highly stressed plant components (single bank rinsing)..

Advantage for customer

  • A permanent and safe supply of process water to the paper mill while reliably complying with all limit values
  • Savings in operating costs due to minimization of required process chemicals and reduced specific water consumption
  • Increase of the "runnability" of the paper machine through higher process water quality
  • Improvement of the product quality
 

Facts and figures

 Commissioning:    2012
 Plant capacitiy:    450 m³/h
 Feed medium:    River water from sand filtration

 

 

 

Process:

Icon Umkehrosmose FINAL        
 Umkehrosmose        

 

We use cookies

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.